Project Economics

Strong technical and commercial viability demonstrated via Etango-8 DFS

  • Conventional open pit mining and heap leach processing at 8Mtpa throughput
  • Informed by vast body of previous technical work across resource drilling, geotechnical, metallurgical and environmental studies
  • Cost estimates completed to +/-10% accuracy and current as at June 2024

Strong technical and commercial viability demonstrated via Etango-8 DFS

15+ years

Initial mine life

8 Mtpa

Throughput capacity

87.8%

Processing yield

52.6 Mlb U3O8

Total production

21.1%

Post-tax IRR

US$390M

Post-tax NPV8%

US$353M

Pre-production capital expenditure

US$39.09/lb

All-in-sustaining-cost (AISC) U3O8

Note: Information and data are reflective of the updated cost estimates from the Control Budget Estimate contained in the ASX release dated 11 June 2024, “Etango-8 FEED Complete and Costs Updated; Detailed Design Commenced”. Post-tax IRR and Post-tax NPV are based on a price assumption of US$80/lb.

Outstanding Etango-8 upside price leverage

Incorporating completion of the Front-End Engineering and Design (FEED) and Control Budget Estimate (CBE) processes

Further in-ground leverage realisable via subsequent growth options

  • Etango can deliver substantially higher value scalability post ramp-up with higher uranium price outcomes, market conditions permitting
  • Etango-XT: Life extension with mine and plant throughput maintained at 8 Mtpa
  • Etango-XP: Mine and plant throughput expanded to 16 Mtpa (expansion capital US$367M)

Further upside price leverage from Etango-XP / XT

Incorporating completion of the Front-End Engineering and Design (FEED) and Control Budget Estimate (CBE) processes1

Keep me updated

Click on the relevant button to sign up for information or to learn more.

Scroll to Top